South Waikato District Plan

15 Designations

15.1 Designations and Outline Plans

(a) The procedure for a notice of requirement is set down in Sections 168 to 175 of the Act.

(b) The Act states that outline plans of public works need not be submitted to Council if:

i) the proposed public work, project, or work has been otherwise approved under this Act or

ii) the details of the proposed public work, are incorporated into the designation (Section 176A) or

iii) the activity is necessary to remove the cause of, or mitigate any actual or likely adverse effect of, an emergency. (Section 330).

(c) Council has the right to waive the requirement for an outline plan and will consider the need for such a plan on a case by case basis upon request from the requiring authority. Outline Plans will not be required in respect of:

i) Any network utility and infrastructure permitted by Section 7 of this plan

ii) Such other works where it is considered impractical or unnecessary to prepare outline plans.

15.2 Public Works Designations

The public works designations applying under this plan are shown on the planning maps and listed below.

The requiring authority may do anything on designated land that is in accordance with the designation, and no other person may do anything in relation to the land without the prior written consent of the requiring authority. (Section 176(1) of the Act).

The rules of this plan shall apply in relation to designated land to the extent that the land is used for purposes other than the designated purpose (Section 176(2)).  The zoning which will apply is shown in the following tables. In respect of highway and railway designations the zoning shall be the same as that of the adjoining land. If the zoning on opposite sides of the highway or railway is different, the centreline shall be the zone boundary.

15.3 Zoning of Roads

Roads other than State Highways are not designated under this plan and are zoned instead. The zoning of roads, and of stopped roads, shall be the same as that of the adjoining land. If the zoning on opposite sides of the road is different, the road centreline shall be the zone boundary.


The designations in the district are listed by Requiring Authority in alphabetical order. The conditions relating to certain designations are provided below the list of designations for each requiring authority. A code has been assigned to each designation, which enables cross-reference to its location on the planning maps. Where the underlying zone shown in the designation schedule differs from the planning maps, the planning maps take precedence.

 

Requiring Authority Identifiers

CNZ

Chorus NZ Ltd

KRH

KiwiRail Holdings Ltd

MEDU

Minister of Education

MJUS

Minister of Justice

NZME

NZME (in respect of the radio networks)

NZTA

New Zealand Transport Agency

PRCO

Powerco Ltd

SWDC

South Waikato District Council

SPK

Spark New Zealand Trading Ltd

TPR

Transpower New Zealand Ltd

 

Requiring Authority: CNZ – Chorus NZ Ltd

In the following Table, ‘Telecommunication’ means telecommunication, radiocommunication and ancillary activities, including existing works, facilities, and future upgrades.

Puketurua Exchange

Designation unique identifier

CNZ01

Designation purpose

Telecommunication

Site identifier

Pearson Rd, Puketurua

Pt Sec 5, Blk VI Puketurua Township,

Blk IX Patetere North SD

Lapse date

Has been given effect

Designation hierarchy under section 177 of the Resource Management Act

Primary

Conditions

Yes – outlined in Table A

Additional information

Underlying Zone: GRUZ

 

Waotu Exchange

Designation unique identifier

CNZ02

Designation purpose

Telecommunication

Site identifier

Waotu Road, Waotu

Pt Lot 2 DP 31897,

Blk XIII Patetere North SD

Lapse date

Has been given effect

Designation hierarchy under section 177 of the Resource Management Act

Primary

Conditions

Yes – outlined in Table A

Additional information

Underlying Zone: GRUZ

 

Okoroire Exchange

Designation unique identifier

CNZ03

Designation purpose

Telecommunication

Site identifier

Okoroire Road, Okoroire

Pt Sec 67,

Blk XV Tapapa SD

Lapse date

Has been given effect

Designation hierarchy under section 177 of the Resource Management Act

Primary

Conditions

Yes – outlined in Table A

Additional information

Underlying Zone: GRUZ

 

Putaruru Exchange

Designation unique identifier

CNZ04

Designation purpose

Telecommunications

Site identifier

Tīrau Road, Putaruru

Pt Secs 8 and 9, Blk V Putaruru Village,

Blk VI Patetere North SD

Lapse date

Has been given effect

Designation hierarchy under section 177 of the Resource Management Act

Primary

Conditions

Yes – outlined in Table A

Additional information

Underlying zone: COMZ

 

Tīrau Exchange

Designation unique identifier

CNZ05

Designation purpose

Telecommunications

Site identifier

Cnr Rose Street and Main Street, Tīrau

Section 2 SO 57617

Lapse date

Has been given effect

Designation hierarchy under section 177 of the Resource Management Act

Primary

Conditions

Yes – outlined in Table A

Additional information

Underlying zone: TCZ

 

Lichfield Exchange

Designation unique identifier

CNZ06

Designation purpose

Telecommunications

Site identifier

Ngatira Road, Lichfield

Pt Sec 9 Blk VI Lichfield Village,

Blk XV Patetere SD

Lapse date

Has been given effect

Designation hierarchy under section 177 of the RMA

Primary

Conditions

Yes – outlined in Table A

Additional information

Underlying Zone: GRUZ

 

Tokoroa Exchange

Designation unique identifier

CNZ07

Designation purpose

Telecommunication (this is a joint designation with Spark New Zealand Trading Ltd)

Site identifier

29-31 Logan Street, Tokoroa

Lot 1 DPS 54346

Lapse date

As been given effect

Designation hierarchy under section 177 of the Resource Management Act

Primary

Conditions

Yes

Additional information

Underlying Zone: TCZ

This is a joint designation with Telecom NZ

Conditions

The designation conditions applying to the use of sites CNZ01 to CNZ07 are as follows:

Site Name

Conditions

Putaruru, Tīrau, and Tokoroa

Masts and Antennas

1 The height of any mast and associated antennas shall not exceed 20m

2.  Antennas mounted on the roof of buildings shall not extend more than 5m above the maximum height of the roof of any existing building.

Noise

3. Any new noise-generating equipment (excluding any electricity alternator required for emergency backup power generation) shall not exceed the following noise limits:

At the boundary with any TCZ or COMZ land.

At any time on any day.

LAeq 55dBA

At the boundary with any GRZ land:

7am – 10pm on any day:

LAeq 50dBA

10pm – 7am on any day:

LAeq 40dBA.

4. Any new noise-generating equipment (excluding any electricity alternator required for emergency backup power generation) shall cumulatively in combination with any other noise-generating equipment on the site not result in any increase in existing noise levels received at any other property boundary where the noise levels in Condition 3 are exceeded.  A noise assessment shall be submitted as part of any outline plan to confirm the existing noise levels and predicted new noise levels to confirm compliance with this condition.

5. For any changes or additions to any electricity alternators on the site, where the noise from all electricity alternators exceeds the noise limits in Condition 3, an outline plan shall be required which demonstrates how the equipment and any mitigation is the best practicable option (BPO) to ensure that noise levels do not exceed a reasonable level, and do not exceed existing noise levels.

Radiofrequency Fields

6. Any equipment transmitting radiofrequency energy shall comply with the exposure levels stated in New Zealand Standard NZS2772.1:1999 at any place where the public has reasonable access.

Outline Plan of Works

7. That an Outline Plan of works shall not be required for any internal building works (excluding equipment generating external noise), like for like replacement of equipment, or for the replacement of any antennas of similar size provided that there is no overall increase in the overall height of the facility.

Putaruru and Tīrau only

Masts and Antennas

No part of any new structure shall protrude through a plane rising at an angle of 45 degrees commencing at an elevation of 3m at the boundary of a GRZ.

Puketurua, Waotu, Okoroire, and Lichfield

Masts and Antennas

The height of any mast and associated antennas shall not exceed 25m

Antennas mounted on the roof of buildings shall not extend more than 5m above the maximum height of the roof of any existing building.

Noise

Any new noise-generating equipment (excluding any electricity alternator required for emergency backup power generation) shall not exceed the following noise limits:

At the notional boundary 20m from the facade of any residential unit on other land:

7am – 10pm on any day:

LAeq 50dBA

10pm – 7am on any day:

LAeq 40dBA

Any new noise-generating equipment (excluding any electricity alternator required for emergency backup power generation) shall cumulatively in combination with any other noise-generating equipment on the site not result in any increase in existing noise levels received at any other property boundary where the noise levels in Condition 3 are exceeded.  A noise assessment shall be submitted as part of any outline plan to confirm the existing noise levels and predicted new noise levels to confirm compliance with this condition.

For any changes or additions to the electricity alternators on the site, where the noise from all electricity alternators exceeds the noise limits in Condition 3, an outline plan shall be required which demonstrates how the equipment and any mitigation is the best practicable option (BPO) to ensure that noise levels do not exceed a reasonable level, and do not exceed existing noise levels.

Radiofrequency Fields

Any equipment transmitting radiofrequency energy shall comply with the exposure levels stated in New Zealand Standard NZS2772.1:1999 at any place where the public has reasonable access.

Outline Plan of Works

That an Outline Plan of works shall not be required for any internal building works (excluding equipment generating external noise), like for like replacement of equipment, or for the replacement of any antennas with antennas of similar size provided that there is no overall increase in the overall height of the facility.

 

Requiring Authority: KRH – KiwiRail Holdings Ltd

Kinleith Branch Railway

Designation unique identifier

KRH01

Designation purpose

Railway

Site identifier

From the northern boundary of the District to Kinleith

Various legal descriptions

Lapse date

Has been given effect

Designation hierarchy under section 177 of the Resource Management Act

Primary

Conditions

No

Additional information

Underlying Zone: As per adjoining zones

 

Rotorua Branch Railway

Designation unique identifier

KRH02

Designation purpose

Railway

Site identifier

From Putaruru to the eastern boundary of the District

Various legal descriptions

Lapse date

Has been given effect

Designation hierarchy under section 177 of the Resource Management Act

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 


Requiring Authority: MEDU – Minister of Education

In the following table, Education means the provision of instruction and/or training and may include such uses as early childhood education services, schools, community education, tertiary educational institutions, work skills training centres, outdoor education centres, sport training establishments and out of school care services and includes their ancillary administrative and support facilities (including cultural, recreational or communal).

Amisfield Primary School

Designation unique identifier

MEDU01

Designation purpose

Education

Site identifier

2 Moffat Road, Tokoroa

Lot 2 DP 398824

Lapse date

Has been given effect

Designation hierarchy under section 177 of the Resource Management Act

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Te Kura Kaupapa Māori o Te Hiringa

Designation unique identifier

MEDU02

Designation purpose

Education

Site identifier

14 Tainui Street, Tokoroa

Lot 244 DPS 12639

Lapse date

Has been given effect

Designation hierarchy under section 177 of the Resource Management Act

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Cargill Open Plan Primary School

Designation unique identifier

MEDU03

Designation purpose

Education

Site identifier

115-119 Grampian Street, Tokoroa

Lots 5, 254 and 255 DPS 22091

Lapse date

Has been given effect

Designation hierarchy under section 177 of the Resource Management Act

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

David Henry Primary School

Designation unique identifier

MEDU04

Designation purpose

Education

Site identifier

4-8 Thompson Street, Tokoroa

Lot 1 DPS 11809

Lapse date

Has been given effect

Designation hierarchy under section 177 of the Resource Management Act

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Forest View High School

Designation unique identifier

MEDU05

Designation purpose

Education

Site identifier

Baird Road, Tokoroa

Pt Lot 34 DP 23867 (comprised of 8.0927ha)

Lapse date

Has been given effect

Designation hierarchy under section 177 of the Resource Management Act

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Lichfield Primary School

Designation unique identifier

MEDU06

Designation purpose

Education

Site identifier

779 Lichfield Road, RD2, Putaruru

Section 27 Blk XV Patetere North SD

Lapse date

Has been given effect

Designation hierarchy under section 177 of the RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Te Wharekura o Te Kaokaoroa o Pātetere

Designation unique identifier

MEDU07

Designation purpose

Education

Site identifier

117 Buckland Street, Putaruru

Pt Section 97 Blk VI Patetere North SD,

Pts Lots 27-29 DP 15900,

Section 196 Blk VI Patetere North SD

Lapse date

Has been given effect

Designation hierarchy under section 177 of the RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Putaruru College

Designation unique identifier

MEDU08

Designation purpose

Education

Site identifier

Junction Street, Putaruru

Lot 10 DP 18021,

Pt Lot 11 DP 18021 (comprising 0.0930ha),

Lots 12-72 DP 18021,

Sec 16 Blk VI Patetere North SD,

Pt Section 97A SO 14762,

CLOSED Road SO 39064,

Land on DP 18453 being Pt Section 99 Blk VI Patetere North SD

Lapse date

Has been given effect

Designation hierarchy under section 177 of the RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Putaruru Primary School

Designation unique identifier

MEDU09

Designation purpose

Education

Site identifier

Kennedy Drive, Putaruru

Pt Section 16 Blk X Patetere North SD

Lapse date

Has been given effect

Designation hierarchy under section 177 of the RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Strathmore Primary School

Designation unique identifier

MEDU10

Designation purpose

Education

Site identifier

27 Strathmore Drive, Tokoroa

Lot 1984 DPS 9267

Lapse date

Has been given effect

Designation hierarchy under section 177 of the RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Tainui Full Primary School

Designation unique identifier

MEDU11

Designation purpose

Education

Site identifier

Tainui Street, Tokoroa

Pt Lot 2 DP 28403 and Pt Lot 19 DP 23865

Lapse date

Has been given effect

Designation hierarchy under section 177 of the RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Te Waotu School

Designation unique identifier

MEDU12

Designation purpose

Education

Site identifier

1274 Waotu Road, RD1, Putaruru

Pt Waotu North 2B

Lapse date

Has been given effect

Designation hierarchy under section 177 of the RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Tīrau Primary School

Designation unique identifier

MEDU13

Designation purpose

Education

Site identifier

69 Main Road, Tīrau

Lot 2 DP 306234,

Pt Lot 106 DP 5043

Lapse date

Has been given effect

Designation hierarchy under section 177 of the RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Tokoroa Central Primary School

Designation unique identifier

MEDU14

Designation purpose

Education

Site identifier

3 Clyde Street, Tokoroa

Pt Lot 698 DPS 2051

Lapse date

Has been given effect

Designation hierarchy under section 177 of the Resource Management Act

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Tokoroa High School

Designation unique identifier

MEDU15

Designation purpose

Education

Site identifier

State Highway 32, Tokoroa

Pt Lot 2 DP 32554,

Lots 8 and 9 DPS 5674

Lapse date

Has been given effect

Designation hierarchy under section 177 of the RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Tokoroa Intermediate School

Designation unique identifier

MEDU16

Designation purpose

Education

Site identifier

State Highway 32, Tokoroa

Pt Lot 2 DP 32554,

Lots 8 and 9 DPS 5674

Lapse date

Has been given effect

Designation hierarchy under section 177 of the RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Tokoroa North Primary School

Designation unique identifier

MEDU17

Designation purpose

Education

Site identifier

29 Paraonui Road, Tokoroa

Pt Lot 6 DP 23866

Lapse date

Has been given effect

Designation hierarchy under section 177 of the Resource Management Act

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Kuranui School

Designation unique identifier

MEDU18

Designation purpose

Education

Site identifier

66 Waiomou Road, Okoroire, Tīrau

Allotment 4 of Section 68 XV Tapapa SD

Lapse date

Has been given effect

Designation hierarchy under section 177 of the RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ


Requiring Authority: MJUS – Minister of Justice

Tokoroa District Court

Designation unique identifier

MJUS01

Designation purpose

Courthouse

Site identifier

Bridge Street, Tokoroa

Section 72, Block VIII Patetere South Survey District

Lapse date

Has been given effect

Designation hierarchy under section 177 of the RMA

Primary

Conditions

No

Additional information

Underlying Zone: TCZ

 

Requiring Authority: NZTA – New Zealand Transport Agency

State Highway (SH) 1

Designation unique identifier

NZTA01

Designation purpose

To undertake all statutory requirements in accordance with the Land Transport Management Act 2003 and the Government Roading Powers Act 1989

Site identifier

From the boundary with Matamata-Piako District, south to the boundary with Taupō District

Lapse date

Has been given effect

Designation hierarchy under section 177 of the RMA

Varies

Conditions

The following conditions apply to the SH1/SH29 intersection:

1. Except as provided for in these conditions and subject to the final design, the Project must be undertaken in general accordance with the following plans and information submitted with the Application dated 26 November 2021:

(a) The Project Drawings in Volume 4: Drawing Set of the Resource Consent Application and Notices of Requirement and Assessment of Effects on the Environment dated 26 November 2021; and

(b) The Landscape Concept Plan provided in the response (dated 15 October 2021) to a section 92 request, and titled Landscape Concept Plan | July 2021 | REV 2 (NTS). Where there may be an inconsistency between the documents listed in this condition and the specific requirements of these conditions, these conditions prevail.

2. Prior to the start of Construction Works, the Requiring Authority must arrange and conduct an on-site meeting including the Project Representative and appropriate contractor representative(s) and the Council. The following information must be made available at the meeting:

(a) Timeframes for key stages of the Construction Works;

(b) Details of the Project Representative(s), including their contact details (phone and email address); and

(c) Contact details of the site contractor and other key contractors.

3. Conditions 1-23 and 25 relate to construction of the Project and only apply during Construction Works. After Completion of Construction, those conditions will no longer apply and can be removed. Condition 24 relates to the establishment of mitigation planting and will be required for 5 years after the Completion of Construction. Following this 5 year period, Condition 24 will no longer apply and can be removed.

3A. If 20 working days have passed since the applicable management plan (or amendments) required under these conditions has been submitted to Council for certification, and the Council has not certified the applicable management plan or amendment, or provided advice that the management plan or amendment is not suitable to certify, the Requiring Authority may commence works in accordance the relevant management plan.

4. (a) The Requiring Authority must prepare a Stakeholder and Communications Management Plan (SCMP) prior to the start of Construction Works. The purpose of the SCMP is to identify how the public and stakeholders (including directly affected and adjacent owners and occupiers of land) will be communicated with throughout the Construction Works. To achieve the purpose, the SCMP must include:

(i) the contact details for the Project representative(s). These details must be on the Project website, or equivalent virtual information source, and prominently displayed at the main entrance(s) to the site(s);

(ii) the procedures for ensuring that there is a contact person available for the duration of the Construction Works, for public enquiries or complaints about the Construction Works;

(iii) methods for engaging with Ngāti Koroki Kahukura, Ngāti Hauā and Raukawa, to be developed in consultation with Ngāti Koroki Kahukura, Ngāti Hauā and Raukawa;

(iv) a list of stakeholders, organisations, businesses and persons who will be communicated with;

(v) methods to communicate the proposed hours of the Construction Works outside of normal working hours and on weekends and public holidays, to surrounding residents; and

(vi) linkages and cross-references to communication methods set out in other conditions and management plan(s) where relevant

(b) The SCMP must be submitted to the Council for information 20 working days prior to the start of Construction Works. 

5. (a) At all times during the Construction Works, a record of any complaints received about the Construction Works must be held in a

complaints register maintained by the Requiring Authority. The complaints register must include:

(i) The date, time and nature of the complaint;

(ii) The weather conditions at the time of the complaint;

(iii) The name, phone number and address of the complainant (unless the complainant wishes to remain anonymous);

(iv) Measures taken to respond to the complaint or confirmation of no action if deemed appropriate (including a record of the response provided to the complainant);

(v) The outcome of the investigation into the complaint; and

(vi) Any other activities in the area, unrelated to the Project that may have contributed to the complaint, such as non-project construction, fires, traffic accidents or unusually dusty conditions generally.

(b) A copy of the complaints register required by this condition must be made available to the Council upon request as soon as practicable after the request is made.

(c) Complaints related to the Construction Works must be responded to as soon as reasonably practicable and as appropriate to the circumstances.

6. (a) The Requiring Authority must prepare a Construction Environmental Management Plan (CEMP) prior to the start of Construction Works. The purpose of the CEMP is to set out the management procedures and construction methods to be undertaken to avoid, remedy or mitigate, as far as practicable, any adverse effects associated with the Construction Works and to ensure compliance with the conditions of this designation. To achieve the purpose, the CEMP must include:

(i) the roles and responsibilities of staff and contractors;

(ii) details of the Project Manager and the Project Representative(s), including their contact details (phone and email address);

(iii) the Construction Works programmes and the staging approach, and the proposed hours of work;

(iv) the proposed site layouts (including construction yards), locations of refuelling activities and construction lighting;

(v) methods for controlling the removal of debris and demolition of construction materials from public roads or places;

(vi) methods for providing for the health and safety of the general public;

(vii) measures to mitigate flood hazard effects such as siting stockpiles out of floodplains, minimising obstruction to flood flows

(viii) procedures for incident management; 

(ix) procedures for the refuelling and maintenance of plant and equipment to avoid discharges of fuels or lubricants to watercourses;

(x) measures to address the storage of fuels, lubricants, hazardous and/or dangerous materials, along with contingency procedures to address emergency spill response(s) and clean up;

(xi) how provision is to be made for a cultural induction programme of the contractor's staff by Ngāti Koroki Kahukura, Ngāti Hauā and Raukawa. The frequency and content of these inductions to be agreed with Ngāti Koroki Kahukura, Ngāti Hauā and Raukawa; and

(xii) methods for amending and updating the certified CEMP as required.

(b) The CEMP must be prepared having regard to the Waka Kotahi Guideline for Preparing Environmental and Social Management Plans (April 2014), or any subsequent version.

(c) At least 20 working days prior to the start of Construction Works, the Requiring Authority must submit the CEMP to the Council for certification that the CEMP satisfies the requirements of this condition.

(d) The Requiring Authority must implement the certified CEMP for the duration of the Construction Works.

(e) Any amendments to the certified CEMP must be confirmed in writing by the Requiring Authority and certified in writing by the Council, prior to the implementation of any amendments proposed.

(f) The Requiring Authority must ensure that a copy of the certified CEMP, including any certified amendments, is kept onsite and this copy is updated within 10 working days of any amendments being certified.

7. (a) The Requiring Authority must prepare a Construction Noise and Vibration Management Plan (CNVMP) prior to the start of Enabling Works or Construction Works. The purpose of the CNVMP is to provide a framework for the development and implementation of the BPO for the minimisation of noise and vibration effects from Enabling Works or Construction Works and must set out how compliance with the construction noise and vibration standards set out in Conditions 8 and 9 below will be achieved, as far as practicable.

(b) The CNVMP must be prepared in accordance with Annex E2 of NZS 6803 and the “State Highway Construction and Maintenance Noise and Vibration Guide” (Waka Kotahi version 1.1, 2019 or any subsequent version)

(c) At least 20 working days prior to the start of Enabling Works or Construction Works, the Requiring Authority must submit the CNVMP to the Council for certification that the CNVMP satisfies the requirements of this condition. 

(d) The Requiring Authority must implement the certified CNVMP for the duration of the Enabling Works and Construction Works.

(e) Any amendments to the certified CNVMP must be confirmed in writing by the Requiring Authority and certified in writing by the Council, prior to the implementation of any amendments proposed.

(f) The Requiring Authority must ensure that a copy of the certified CNVMP, including any certified amendments, is kept onsite and this copy is updated within 10 working days of any amendments being certified

8. Noise from any Enabling Works or Construction Works must comply with the following limits in accordance with NZS 6803 as far as practicable:

Day of week

Time

dB LAeq(15min)

dB LAmax

Buildings containing activities sensitive to noise

Weekdays

0630 – 0730

55

75

0730 – 1800

70

85

1800 – 2000

65

80

2000 – 0630

45

75

Saturdays

0630 – 0730

45

75

0730 – 1800

70

85

1800 – 2000

45

75

2000 – 0630

45

75

Sundays and Public Holidays

0630 – 0730

45

75

0730 – 1800

55

85

1800 – 2000

45

75

2000 – 0630

45

75

Other occupied buildings

All days

0730 – 1800

70

n/a

 

1800 – 0730

75

n/a

 

9. Vibration from any Enabling Works or Construction Works must comply with the following limits. The Category A limits must be complied with as far as practicable and the Category B limits must be complied with at all times:

Receiver Category

Details

Category A

Category B

Occupied Activities sensitive to noise

Night-time 2000h - 0630h

0.3mm/s ppv

1mm/s ppv

Daytime 0630h - 2000h

1mm/s ppv

5mm/s ppv

Other occupied buildings

Daytime 0630h - 2000h

2mm/s ppv

5mm/s ppv

All other buildings

At all other times

5mm/s ppv

Tables 1 and 3 of DIN4150- 3:1999

DIN4150-3:1999-02 Structural Vibration Part 3: Effects of vibration on structures

Advisory Note: Measurements of construction vibration must be undertaken in accordance with ISO 4866:2010 Mechanical vibration and shock – Vibration of fixed structures – Guidelines for the measurement of vibrations and evaluation of their effects on structures.

10. (a) If during any Enabling Works or Construction Works noise or vibration levels from the Construction Works are predicted or known to exceed the noise limits in Condition 8 above or the Category A vibration limits in Condition 9 above, the Requiring Authority must consult with the affected receivers or those predicted to be affected to:

(i) Discuss the nature of the work and the anticipated days and hours when the exceedances are likely to occur;

(ii) Determine whether the exceedances could be timed or managed to reduce the effects on the receiver.

(b) The process and outcomes of (i) and (ii) must be described in detail and added as a schedule(s) to the CNVMP and implemented by the Requiring Authority for the duration of the relevant works.

(c) The schedule(s) must be provided to the Council for information within five working days where practicable before the specific construction activity is undertaken. 

10A. The Requiring Authority must ensure that construction yards are located at least 70m from the notional boundary of any PPF. If a construction yard is required to be established closer than 70m, the Requiring Authority must implement the process set out in Condition 10 in accordance with Condition 7

11. The Requiring Authority must prepare a Construction Traffic Management Plan (CTMP) prior to the start of Construction Works in accordance with Waka Kotahi’s Code of Practice for Temporary Traffic Management. The purpose of the CTMP is to avoid, remedy or mitigate, as far as practicable, adverse construction traffic effects of the Project. To achieve this purpose, the CTMP must include methods to maintain vehicle access to property where practicable, or to provide alternative access arrangements when maintaining vehicle access is not practicable. The Requiring Authority must provide the CTMP to Council for information prior to the start of Construction Works.

11A. As part of the Outline Plan of Works, the Requiring Authority must describe how the following matters have been addressed:

(a) Indicative safe stopping locations for school buses on the roads approaching the SH1/29 intersection during Construction Works and following Completion of Construction;

(b) Arrangements for farm vehicle access including milk tankers.

(c) Oversize vehicle manoeuvring; and

(d) Measures to prevent public use of slip roads and private property access as short cuts (i.e. during peak traffic).

11B. Following detailed design, and prior to the start of Construction Works, the Requiring Authority must submit to the Council for information an independent road safety audit completed in accordance with Waka Kotahi Road safety audit procedures for projects (Guidelines, Interim release May 2013).

Advice Note: The Requiring Authority expects the independent road safety audit will include specific assessment of:

(a) Truck stability;

(b) Oversize vehicles;

(c) Provision of infrastructure to assist in the management of special event traffic;

(d) Farm vehicle and tanker access; and

(e) School buses

12. The Requiring Authority must manage the Construction Works so that they do not adversely impact on the ongoing safe and efficient operation of Network Utility Operations. The scope, timing and methodology for utility protection and / or relocation works must be developed in consultation with the relevant Network Utility Operator to ensure ongoing safe and efficient operation for the required works.

13. Temporary and permanent works must be designed to mitigate Earth Potential Rise (EPR) where the use of conductive materials for road infrastructure (e.g. metallic barriers, lighting, noise walls) or relocated network utilities are within 50 metres of the Hinuera - Karapiro A (HINKPO-A) 110kV transmission assets.

14. Temporary and permanent works must be designed so that the vertical clearance provided between the transmission line conductors and the finished road level is a minimum of 9.5 metres for the HIN-KPO-A 110kV transmission line

15. Temporary and permanent works must be designed to maintain a comparable standard of access to the HIN-KPO-A 110kV transmission assets for maintenance at all reasonable times, and emergency works at all times.

16. Proposed planting and the ongoing maintenance of trees and vegetation in the vicinity of overhead transmission lines must comply with the Electricity (Hazards from Trees) Regulations 2003.

17. Species planted within 12 metres of the centreline of the HIN-KPO-A 110kV transmission line must not exceed 2 metres in height. When planted, trees (at full maturity height) must not be able to fall within 4 metres of a transmission line conductor at maximum swing.

18. Prior to the start of Construction Works, an Electrical Infrastructure Management Plan (EIMP) must be prepared for Construction Works within 50 metres of the HIN-KPO-A 110kV transmission assets. The EIMP must be prepared by a Suitably Qualified Person in consultation with Transpower. The purpose of the EIMP is to set out the management procedures and construction methods to be undertaken so that works are safe and any potential adverse effects of works on Transpower assets are appropriately managed.

19. To achieve the purpose, the EIMP must include:

(a) Roles and responsibilities of staff and contractors responsible for implementation of the EIMP.

(b) Drawings showing proposed works in the vicinity of, or directly affecting, the HIN-KPO A 110kV transmission assets.

(c) Proposed staff and contractor training for those working near the transmission assets.

(d) Proposed methods to comply with Design Conditions 13-15 above

(e) Proposed methods to comply with the New Zealand Electrical Code of Practice for Electrical Safe Distances 2001 (NZECP 34: 2001).

(f) Dispensations agreed with Transpower for any Construction Works that cannot meet New Zealand Electrical Code of Practice for Electrical Safe Distances 2001 (NZECP 34:2001).

(g) Proposed methods to:

(i) Delineate areas that are out of bounds during construction and areas within which additional management measures are required, such as fencing off, entry and exit hurdles, maximum height limits, or where a Transpower observer may be required.

(ii) Manage the effects of dust (including any other material potentially resulting from construction activities able to cause material damage beyond normal wear and tear) on the transmission lines.

(iii) Manage any changes to drainage patterns, runoff characteristics and stormwater to avoid adverse effects on foundations of any support structure.

(iv) Manage construction activities that could result in ground vibrations and/or ground instability to avoid causing damage to transmission lines and support structures

20. The EIMP must include confirmation that it has been reviewed and endorsed by Transpower and must be submitted to Council for information

21. Construction Works must not commence within 50 metres of the HINKPO-A 110kV transmission assets until the EIMP required by Condition 18 above has been completed and either:

(a) the Project has been designed to comply with Design Conditions 13 - 15 above; or

(b) the HIN-KPO-A 110kV transmission assets have been relocated or altered as agreed by Transpower.

22. Construction Works must be undertaken in accordance with the EIMP requited by Condition 18 above.

Advice Notes:

(a) Written notice should be provided to Transpower 10 working days before starting works within 50 metres of transmission assets. Written notice should be sent to transmission.corridor@transpower.co.nz

(b) Temporary and permanent works in the vicinity of overhead transmission assets shall be designed and undertaken to comply with the New Zealand Electrical Code of Practice for Electrical Safe Distances (NZECP 34:2001)

23. (a) The Requiring Authority must prepare in collaboration with Ngāti Koroki Kahukura Trust, Ngāti Hauā Trust and Raukawa Settlement Trust a Landscape Concept Plan (LCP) prior to the start of Construction Works. The LCP must be prepared by a Suitably Qualified Person. The purpose of the LCP is to establish a framework for the integration of the permanent Project into the surrounding environment. The LCP must address the following landscape design factors:

(i) Ensure that the Project’s landscape treatments are contextsensitive in terms of acknowledging Ngāti Koroki Kahukura Trust, Ngāti Hauā Trust and Raukawa Settlement Trust values, landforms, land use, sense of place and the viewing audience;

(ii) Ensure that the Project’s landscape treatments function to address amenity, as well as support road safety, biodiversity and stormwater management;

(iii) Provide safe connectivity for cyclists and pedestrians;

(iv) Appropriate design treatment(s) to support safety and wayfinding; and

(v) Crime Prevention Through Environmental Design CPTED) principles, where practicable.

(b) The LCP must include a summary of the engagement undertaken with Ngāti Koroki Kahukura Trust, Ngāti Hauā Trust and Raukawa Settlement Trust and how any feedback has been incorporated into the LCP, and an explanation of where and why any feedback has not been incorporated into the LCP.

(c) At least 20 working days prior to the start of Construction Works, the Requiring Authority must submit the LCP to the Council for certification that the LCP satisfies the requirements of this condition.

(d) The Requiring Authority must implement the certified LCP.

(e) Any amendments to the certified LCP must be confirmed in writing by the Requiring Authority and certified in writing by the Council, prior to the implementation of any amendments proposed

24. (a) The Requiring Authority must prepare in collaboration with Ngāti Koroki Kahukura Trust, Ngāti Hauā Trust and Raukawa Settlement Trust a Detailed Planting Plan (DPP) for the Project prior to the start of Construction Works.

(b) The DPP must be prepared to implement the LCP in accordance with the Waka Kotahi NZ Transport Agency Highway Landscape Guidelines and P39 – Standard Specification for Highway Landscape Treatments, and include the following:

(i) All planting zones and layouts

(ii) Species list, including native eco-sources species and specimen trees. With the grades of plants at the time of planting and an indication of their height at maturity; and

(iii) An indication of site preparation, subsoil and topsoil and mulch treatments.

(c) The DPP must include a summary of the engagement undertaken with Ngāti Koroki Kahukura Trust, Ngāti Hauā Trust and Raukawa Settlement Trust and how this has been incorporated into the DPP and an explanation of where and why any feedback has not been incorporated into the DPP.

(d) At least 20 working days prior to the start of Construction Works, the Requiring Authority must submit the DPP to the Council for certification that the DPP satisfies the requirements of this condition.

(e) The Requiring Authority must implement the certified DPP and thereafter maintain this planting and associated landscape works for 5 years following the Completion of Construction to ensure that the mitigation is properly established. After this 5 year period, the Requiring Authority must add the areas in the DPP to its Network Outcome Contract for this section of the State Highway to require maintenance of the planting and associated landscape.

(f) Any amendments to the certified DPP must be confirmed in writing by the Requiring Authority and certified in writing by the Council, prior to the implementation of any amendments proposed

25. Prior to the commencement of Enabling Works, the Requiring Authority must provide to the Council, evidence that an Archaeological Authority (or Authorities) under the Heritage New Zealand Pouhere Taonga Act 2014 has been obtained from Heritage New Zealand Pouhere Taonga as appropriate, to modify or destroy any of the unknown archaeological sites likely to be affected during the Enabling Works or Construction Works.

26. Lighting of the intersection must comply with AS/NZS 1158: Lighting for roads and public spaces.

27. Lighting of the intersection must meet the following thresholds: (i) LED colour temperature must not exceed 2700 Kelvins; and (ii) Light levels must not exceed 0.3 lux at the boundary of key bat habitats shown in as a white line in Figure 1 of the Environment Court decision [2023] NZEnvC 064 dated 17 April 2023.

 

Additional information

  • Underlying Zone: As per zoning of adjoining land
  • The following sections of State Highway 1 are a Limited Access Road, as declared under Section 88 of the Government Roading Powers Act 1989:
  • Maungatautari Road to Waitoa Flats, Gaz 1972 p 1215
  • Waitoa Flats to Tirau Town boundary, Gaz 1972 p 2847
  • SH 5 to Oraka Stream Bridge at Putaruru, Gaz 1968 p 2253
  • Putaruru Railway overbridge to Ngutuwera Stream bridge, Gaz 1974 p 2546
  • Ngutuwera Stream bridge to Pokaiwhenua Stream bridge, Gaz 1997 p 1132
  • Pokaiwhenua Stream bridge to Whakauru Stream bridge, Gaz 1969 p 1338
  • Campbell Road to Matarawa Stream bridge, Gaz 1969 p 1223
  • Matarawa Stream bridge to SH 30, Gaz 1996 p 1830
  • SH 30 to Atiamuri River bridge, Gaz 1996 p 1761

 

State Highway (SH) 5

Designation unique identifier

NZTA02

Designation purpose

To undertake all statutory requirements in accordance with the Land Transport Management Act 2003 and the Government Roading Powers Act 1989

Site identifier

From the intersection with SH1, east to the boundary with Rotorua Lakes District

Lapse date

Has been given effect

Designation hierarchy under section 177 of the RMA

Primary

Conditions

No

Additional information

1. Underlying Zone: GRUZ

2. The following sections of State Highway 5 are a Limited Access Road, as declared under Section 88 of the Government Roading Powers Act 1989:

  • SH 1 to Waimakariri River bridge, Gaz 1999 p 1432
  • Waimakariri River bridge to Region boundary, Gaz 2000 p 4056

 

 

State Highway (SH) 27

Designation unique identifier

NZTA03

Designation purpose

To undertake all statutory requirements in accordance with the Land Transport Management Act 2003 and the Government Roading Powers Act 1989

Site identifier

From the intersection with SH1, north to the boundary with Matamata-Piako District

Lapse date

Has been given effect

Designation hierarchy under section 177 of the RMA

Primary

Conditions

No

Additional information

1. Underlying Zone: As per zoning of adjoining land

2. The following section of State Highway 27 is a Limited Access Road, as declared under Section 88 of the Government Roading Powers Act 1989:

  • SH 29 to Tirau Town boundary, Gaz 1996 p 1520

 

State Highway (SH) 28

Designation unique identifier

NZTA04

Designation purpose

To undertake all statutory requirements in accordance with the Land Transport Management Act 2003 and the Government Roading Powers Act 1989

Site identifier

From the intersection with SH1, north to the boundary with Matamata-Piako District

Lapse date

Has been given effect

Designation hierarchy under section 177 of the Resource Management Act

Primary

Conditions

No

Additional information

1. Underlying Zone: GRUZ

2. The following section of State Highway 28 is a Limited Access Road, as declared under Section 88 of the Government Roading Powers Act 1989:

  • SH 5 to Brown Road, Gaz 2000 p 4056

 

State Highway (SH) 30

Designation unique identifier

NZTA05

Designation purpose

To undertake all statutory requirements in accordance with the Land Transport Management Act 2003 and the Government Roading Powers Act 1989

Site identifier

From the intersection with SH32, east to the boundary with Rotorua Lakes District

Lapse date

Ha been given effect

Designation hierarchy under section 177 of the Resource Management Act

Primary

Conditions

No

Additional information

1. Underlying Zone: GRUZ

2. The following section of State Highway 30 is a Limited Access Road, as declared under Section 88 of the Government Roading Powers Act 1989:

  • South Waikato / Rotorua District boundary to Rotorua Gun Club, Gaz 2002 p 1035

 

State Highway (SH) 32

Designation unique identifier

NZTA06

Designation purpose

To undertake all statutory requirements in accordance with the Land Transport Management Act 2003 and the Government Roading Powers Act 1989

Site identifier

From the intersection with SH1, south to the boundary with Taupō District

Lapse date

Has been given effect

Designation hierarchy under section 177 of the Resource Management Act

Primary

Conditions

No

Additional information

Underlying Zone: As per zoning of adjoining land

 


Requiring Authority: PRCO – Powerco Ltd

Putaruru Substation

Designation unique identifier

PRCO01

Designation purpose

Zone substation

Site identifier

Arapuni Street, Putaruru

Lot 1 DPS 8454 and being Pt Sec 14 Selwyn Settlement, Section 1 SO 535093.

Lapse date

Has been given effect

Designation hierarchy under section 177 of the RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Distribution Substation

Designation unique identifier

PRCO02

Designation purpose

Distribution substation

Site identifier

Market Street, Putaruru

Pt Mangakaretu No 1 Block

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: COMZ

 

Distribution Substation

Designation unique identifier

PRCO03

Designation purpose

Distribution substation

Site identifier

Duke Street – Arapuni Street, Putaruru

Pt Lot 45 DPS 14428

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: COMZ

 

Baird Road Substation

Designation unique identifier

PRCO04

Designation purpose

Zone substation

Site identifier

20 Whakauru Street, Tokoroa

Lot 1 DPS 8532

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: COMZ

 

Maraetai Road Substation

Designation unique identifier

PRCO05

Designation purpose

Zone substation

Site identifier

State Highway 32 and Aotea Crescent, Tokoroa

Lot 1 DPS 10546

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Tīrau Substation

Designation unique identifier

PRCO06

Designation purpose

Zone Substation

Site identifier

Okoroire Street, Tīrau

Lot 1 DPS 60650

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GIZ

 

Kinleith Ripple Control Plant

Designation unique identifier

PRCO07

Designation purpose

Ripple injection load control plant

Site identifier

Old Taupo Road, Kinleith

SO 45546

Lapse date

Has been given effect

Designation hierarchy under section 177 of the Resource Management Act

Primary

Conditions

No

Additional information

Underlying Zone: GIZ

 

Lakeside Pump Substation

Designation unique identifier

PRCO08

Designation purpose

Zone substation

Site identifier

Landing Road, Maraetai

Undivided portion of Lot 1-2 DP 20269

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Midway Substation

Designation unique identifier

PRCO09

Designation purpose

Zone substation

Site identifier

Kopakorahi Road, Kinleith

Undivided portion of DP 19831, DP 19832, DP 19833

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 


Requiring Authority: NZME – Radio Networks

Wiltsdown Transmitter Site

Designation unique identifier

NZME01

Designation purpose

Radiocommunication, Telecommunication (including broadcasting), and Ancillary Purposes and Land Uses

Site identifier

Wiltsdown Road, Tokoroa

Part Lot 1 DP 13665, Block II Patetere South SD

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

Yes

Additional information

Underlying Zone: GRUZ

 

Conditions

1) There shall be only one lattice tower on the designated land, with a maximum height of 120m above existing ground level, at any one time with the exception of temporary structures for construction and/or maintenance purposes. Any temporary structures shall be removed at the end of such work.

The emission of electrical or electromagnetic radiation shall comply with the New Zealand Standard NZS2772.1 (1999): Radio frequency Fields: Part 1 Maximum Exposure Levels – 3kHz – 300GHz.

2) The placement or erection of the following equipment on the lattice tower and existing structures on the site shall be permitted without the provision of any outline plan of works pursuant to section 176A(1) of the Resource Management Act 1991:

(a) Broadcasting, telecommunication, and radiocommunication antennas including whip, grid, yagi, dipoles and panels or similar ancillary equipment, but no single antenna dish or panel shall have a solid frontal surface area of greater than 4m2 or 2m in diameter in the case of dish antenna, unless otherwise specified above.

(b) No new structures other than those permitted under the district plan or as specified in Condition 2(a) above shall be erected on the site without the submission of an outline plan of works pursuant to section 176A of the Resource Management Act 1991.

(c) Any new antenna or structures above 10 metres in height shall be constructed from materials which minimise the reflection of light (subject to civil aviation requirements).

(d) All activities shall be conducted and buildings located, designed and used to ensure that noise levels at or within the notional boundary of the nearest building do not exceed the following limits:

3) Maximum Noise Levels

(a) Monday to Friday 7.00 am – 7.00pm: 45 dBA L10

(b) Saturday 7.00 am – 6.00pm: 45 dBA L10

(c) At all other times including Public Holidays: 40 dBA L10 75 dBA Lmax

Noise shall be measured and addressed in accordance with New Zealand Standards:

(i). NZS 6801:1991 – Measurement of Sound

(ii). NZS 6802: 1991 – Assessment of Environmental Sound

ADVICE NOTE: Notional Boundary as referred to in this condition means a line 20 metres from the façade of any rural dwelling. Except that where a rural dwelling is not situated on the same title as Radio New Zealand Limited’s facilities, the notional boundary means:

(iii). a line 20 metres from the façade of that rural dwelling; or

(iv). the legal boundary of the title on which that rural dwelling is situated, whichever is the closer to the rural dwelling.

4) That during any construction work carried out at the site, the requiring authority shall ensure that the builders operate their plant and equipment in compliance with NZS 6803P Measurement and Assessment of Noise from Construction, Maintenance and Demolition Work.

5) The above conditions do not restrict the continued use of infrastructure currently on the designated land, subject to compliance with the noise limits stated in condition 3 and emission levels specified in condition 1 including those specified in item 3.1 of the Notice of Requirement. This infrastructure includes (but is not limited to):

(a) An aerial mast approximately 110m high, with synthetic support guys, which currently operates three AM signals, and FM antennas which currently operate four FM signals;

(b) An Aerial Coupling Unit (ACU) Hut;

(c) An FM Transmitter Hut;

(d) A radial earth mat which forms part of the aerial system;

(e) Aerial security fencing approximately 2 metres in height;

(f) A concrete block AM transmissions building approximately 4 x 8 metres in dimension;

(g) A diesel generator building of concrete block construction;

(h) Stock fencing around the transmissions and generator buildings;

(i) Associated power supply, wires and cables; and

(j) Road access.

That the existing radio and telecommunication aerials and any new aerials shall be surrounded by security fencing at least 2m in height and any gate into this area shall be kept locked at all times.

 

Requiring Authority: SPK – Spark New Zealand Trading Ltd

In the following table, ‘Telecommunication’ means telecommunication, radiocommunication, and ancillary activity, including existing works, facilities, and future upgrades.

Tokoroa Exchange

Designation unique identifier

SPK01

Designation purpose

Telecommunication

Site identifier

29-31 Logan Street, Tokoroa

Lot 1 DPS 54346

Lapse date

Has been given effect to

Designation hierarchy under section 177 RMA

Primary

Conditions

Yes

Additional information

Underlying Zone: TCZ

This is a joint designation with Chorus NZ Ltd

Conditions

The designation conditions applying to the use of site SPK01 are as follows:

Masts and Antennas

1) The height of any mast and associated antennas shall not exceed 20m

2) Antennas mounted on the roof of buildings shall not exceed more than 5m above the maximum height of the roof of any existing building

Noise

1) Any new noise-generating equipment (excluding any electricity alternator required for emergency back-up power generation) shall not exceed the following noise limits:

  • At the boundary with any TCZ or COMZ land;
  • At any time of day;
  • Leq 55dBA
  • At the boundary with any Residential zoned land;
  • 7am – 10pm on any day;
  • Leq 50dBA
  • 10pm – 7am on any day;
  • Leq 40dBa

4) Any new noise-generating equipment (excluding any electricity alternator required for emergency back-up power generation) shall cumulatively in combination with any other noise-generating equipment on the site not result in any increase in existing noise levels received at any other property boundary where the noise levels in Condition 3 are exceeded. A noise assessment shall be submitted as part of any outline plan to confirm the existing noise levels and predicted new noise levels to confirm compliance with this condition.

5) For any changes or additions to any electricity alternators exceeds the noise limits in Condition 3, an outline plan shall be required which demonstrates how the equipment and any mitigation is the best practicable option (BPO) to ensure that the noise levels do not exceed a reasonable level, and do not exceed existing noise levels.

Radiofrequency Fields

6) Any equipment transmitting radiofrequency energy shall comply with the exposure levels stated in New Zealand Standard NZS2772.1:1999 at any place where the public had reasonable access.

Outline Plan of Works

That an Outline Plan of Works shall not be required for any internal building works (excluding equipment generating external noise), like for like the replacement of equipment, or for the replacement of any antennas of similar size provided that there is no overall increase in the overall height of the facility.

 

Requiring Authority: SWDC – South Waikato District Council

Wastewater Treatment Plants

Tokoroa Wastewater Treatment Plant

Designation unique identifier

SWDC01

Designation purpose

Wastewater treatment plant

Site identifier

Whakauru Street, Tokoroa

Pt Lot 6 DP23866

Lapse date

Has been given effect

Designation hierarchy under section 177 of RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Putaruru Wastewater Treatment Plant

Designation unique identifier

SWDC02

Designation purpose

Wastewater treatment plant

Site identifier

Peace Street, Putaruru

Pt Lot 1 DP 18021, Public Road

Lapse date

Has been given effect

Designation hierarchy under section 177 of RMA

Primary

Conditions

No

Additional information

Underlying Zone: COMZ and GRUZ

 

Tīrau Wastewater Treatment Plant

Designation unique identifier

SWDC03

Designation purpose

Wastewater treatment plant

Site identifier

State Highway 27, Tīrau

Pt Lot 106 DP 5043

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GIZ

 

Arapuni Wastewater Treatment Plant

Designation unique identifier

SWDC04

Designation purpose

Wastewater treatment plant

Site identifier

Powerhouse Road, Arapuni

Lot 109 DPS 64351

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Wastewater Treatment Plant Drainage Field

Designation unique identifier

SWDC05

Designation purpose

Wastewater treatment plant drainage field

Site identifier

Powerhouse Road, Arapuni

Stopped Road, SO4682

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: SPZ-ELG

 

Montgomerie Tank

Designation unique identifier

SWDC06

Designation purpose

Sewage treatment

Site identifier

Arapuni Road, Arapuni

Lot 108 DPS 64353

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: MU-SETZ

 

Pump Stations

Sewage Pump Station

Designation unique identifier

SWDC07

Designation purpose

Sewage pump station

Site identifier

Off West Parkdale Street, Tokoroa

Lot 3 DPS 31442

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Sewage Pump Station

Designation unique identifier

SWDC08

Designation purpose

Sewage pump station

Site identifier

Northfield Place, Tokoroa

Pt Lot 201 DPS 14341

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Sewage Pump Station

Designation unique identifier

SWDC09

Designation purpose

Sewage pump station

Site identifier

Tasman Drive, Tokoroa

Lot 88 DPS 11783

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Sewage Pump Station

Designation unique identifier

SWDC10

Designation purpose

Sewage pump station

Site identifier

Croad Place, Tokoroa

Pt Lot 7 DPS 18609

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: COMZ

 

Sewage Pump Station

Designation unique identifier

SWDC11

Designation purpose

Sewage pump station

Site identifier

Baird Road, Tokoroa

Pt Lot 95 DPS 11784 and Public Road

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Sewage Pump Station

Designation unique identifier

SWDC12

Designation purpose

Sewage pump station

Site identifier

Chartwell Drive, Tokoroa

Lot 129 DPS 18497

Lapse date

 

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Sewage Pump Station

Designation unique identifier

SWDC13

Designation purpose

Sewage pump station

Site identifier

Mossop Road, Tokoroa

Pt Lot 6 DPS 2424

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Sewage Pump Station

Designation unique identifier

SWDC14

Designation purpose

Sewage pump station

Site identifier

Galway Cres, Putaruru

Section 102

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Sewage Pump Station

Designation unique identifier

SWDC15

Designation purpose

Sewage pump station

Site identifier

Buckland Street, Putaruru

Lot 1 DPS 8360

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Sewage Pump Station

Designation unique identifier

SWDC16

Designation purpose

Sewage pump station

Site identifier

Grey Street, Putaruru

Lot 11 DPS 5800

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Sewage Pump Station

Designation unique identifier

SWDC17

Designation purpose

Sewage pump station

Site identifier

Overdale Street, Putaruru

Lot 21 DPS 8634

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Sewage Pump Station

Designation unique identifier

SWDC18

Designation purpose

Sewage pump station

Site identifier

Market Street, Putaruru

Public Road

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GIZ

 

Sewage Pump Station

Designation unique identifier

SWDC19

Designation purpose

Sewage pump station

Site identifier

Taupo Street, Putaruru

Pt Lot 1 DPS 17490

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Sewage Pump Station

Designation unique identifier

SWDC20

Designation purpose

Sewage pump station

Site identifier

Bear Street, Tīrau

Public Road

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Sewage Pump Station

Designation unique identifier

SWDC21

Designation purpose

Sewage pump station

Site identifier

Depot Street, Tīrau

Pt Sec 46

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GIZ

 

Sewage Pump Station

Designation unique identifier

SWDC22

Designation purpose

Sewage pump station

Site identifier

Satco Drive, Tokoroa

Lot 1 DPS 408179

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GIZ

 

Sewage Pump Station

Designation unique identifier

SWDC23

Designation purpose

Sewage pump station

Site identifier

Parapara Road, Tīrau

Public Road

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: RLZ

Refuse Sites

Tokoroa Refuse Disposal Site

Designation unique identifier

SWDC24

Designation purpose

Refuse disposal and recycling site and hazardous waste transfer station

Site identifier

Newell Road, Tokoroa

Pt Lot 2 DP 34291

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Putaruru Refuse Disposal Site

Designation unique identifier

SWDC25

Designation purpose

Refuse disposal site

Site identifier

2199 State Highway 1, Putaruru

Sec 1 SO 429412

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GIZ

 

Tīrau Refuse Disposal Site

Designation unique identifier

SWDC26

Designation purpose

Refuse disposal site

Site identifier

Sec 1 SO 429412, State Highway 1, Tīrau

Pt Lot 1 Sec 3

Pt Lot 15 DP5043

Pt Lot 100 DPS 5043

Lot 3 DPS 13028

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Reservoirs

Water Supply Reservoir and Treatment Station

Designation unique identifier

SWDC27

Designation purpose

Water supply reservoir and treatment station

Site identifier

Billah Street, Tokoroa

Pt Lot 52

Lots 53 and 54 DPS 3892

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Water Supply Reservoirs (2)

Designation unique identifier

SWDC28

Designation purpose

Water supply reservoirs

Site identifier

Lion Drive, Tokoroa

Pt Lot 3 DP 22967

Lot 1 DPS 27686

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Water Supply Reservoir

Designation unique identifier

SWDC29

Designation purpose

Water supply reservoir

Site identifier

Pinedale Road, Putaruru

Pt lot 1 of Sec 36

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Water Supply Reservoir

Designation unique identifier

SWDC30

Designation purpose

Water supply reservoir

Site identifier

Reservoir Street, Putaruru

Pt Lot 1 DP 15603

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Water Supply Reservoir

Designation unique identifier

SWDC31

Designation purpose

Water supply reservoir

Site identifier

Fairview Street, Tīrau

DP 27220

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Water Supply Reservoir

Designation unique identifier

SWDC32

Designation purpose

Water supply reservoir

Site identifier

Pioneer Crescent, Arapuni

Lot 100 DPS 64358

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: MU-SETZ

 

Headworks

Water Supply Bore

Designation unique identifier

SWDC33

Designation purpose

Water supply

Site identifier

Ngatira Road, Lichfield

Pt Sec 7 Blk VI, Village of Lichfield

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Water Supply Headworks

Designation unique identifier

SWDC34

Designation purpose

Water supply headworks

Site identifier

Princess Beatrix Avenue, Tokoroa

Lot 1 DPS 30711

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Water Supply Headworks

Designation unique identifier

SWDC35

Designation purpose

Water supply headworks

Site identifier

Elizabeth Drive, Tokoroa

Pt Lot 40 DPS 9464

Pt Lot 11 DPS 4637

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Water Supply Headworks

Designation unique identifier

SWDC36

Designation purpose

Water supply headworks

Site identifier

State Highway 1, Tīrau

Public Road

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Water Supply Headworks

Designation unique identifier

SWDC37

Designation purpose

Water supply headworks

Site identifier

Arapuni Road, Arapuni

SO 59585

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Water Supply Booster Pump House

Designation unique identifier

SWDC38

Designation purpose

Water supply booster pump house

Site identifier

Pioneer Crescent, Arapuni

Lot 77 DPS 64359

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: MU-SETZ

 

Blue Spring Water Supply

Designation unique identifier

SWDC39

Designation purpose

Water supply

Site identifier

Leslie Road, Putaruru

Public Road

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Detention Dams

Stormwater Detention Dam

Designation unique identifier

SWDC40

Designation purpose

Stormwater detention dam

Site identifier

State Highway 1, Putaruru

Pt Sec 19

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Stormwater Detention Dam

Designation unique identifier

SWDC41

Designation purpose

Stormwater detention dam

Site identifier

State Highway 1, Putaruru

Pt Sec 19

Lot 1 DP 34653

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Stormwater Detention Dam

Designation unique identifier

SWDC42

Designation purpose

Stormwater detention dam

Site identifier

Kennedy Drive, Putaruru

Pt Lot 3 DPS 21758

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: RLZ

 

Stormwater Detention Dam

Designation unique identifier

SWDC43

Designation purpose

Stormwater detention dam

Site identifier

Grampian Street, Tokoroa

Pt Lot 1 DPS 44913

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Stormwater Detention Dam

Designation unique identifier

SWDC44

Designation purpose

Stormwater detention dam

Site identifier

St Andrews Drive, Tokoroa

Pt Lot 1983 DPS 9267

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Lake Moananui Dam

Designation unique identifier

SWDC45

Designation purpose

Dam

Site identifier

Arawa Crescent, Tokoroa

Pt Lot 1 DPS 17335

Pt Lot 514 DPS 15337

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Cemeteries

Amisfield Cemetery

Designation unique identifier

SWDC46

Designation purpose

Cemetery

Site identifier

Dumfries Road, Tokoroa

Lots 30 and 31 DPS 2883

Pt Lot 1 DPS 82621, Lot 1 DP568751

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Old Putaruru Cemetery

Designation unique identifier

SWDC47

Designation purpose

Cemetery

Site identifier

Tīrau Street, Putaruru

Section 98 Block VI Patetere North SD

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Domain Road Cemetery

Designation unique identifier

SWDC48

Designation purpose

Cemetery

Site identifier

Domain Road, Putaruru

Secs 3 4 & Pt Sec 5 SO429412

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GIZ

 

Tīrau Cemetery

Designation unique identifier

SWDC49

Designation purpose

Cemetery

Site identifier

Okoroire Road, Tīrau

Lots 1 and 2 DPS 13602

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Putaruru Office and Library

Putaruru Office and Library

Designation unique identifier

SWDC50

Designation purpose

Office and Library

Site identifier

Overdale Street, Putaruru

Pt Secs 13 and 14

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: COMZ

 

Stormwater Detention

Stormwater Detention Area

Designation unique identifier

SWDC51

Designation purpose

Stormwater detention area

Site identifier

Goodwin Street, Tīrau

Lot 9 DPS 407499

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Stormwater Detention Area

Designation unique identifier

SWDC52

Designation purpose

Stormwater detention area

Site identifier

Bent Street, Putaruru

Lot 2 DPS 34983

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRZ

 

Stormwater Detention Area

Designation unique identifier

SWDC53

Designation purpose

Stormwater detention area

Site identifier

Barnett Street, Putaruru

Pt Lot 21 DPS 7103

Lot 4 DPS 64289

Lot 2 DPS 76668

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: RLZ 

 

Stormwater Detention Area

Designation unique identifier

SWDC54

Designation purpose

Stormwater detention area

Site identifier

Strathmore Park/ Huttloc Drive, Tokoroa

Lot 5 DP 407781

Lots 1-3 DPS 44913

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ and GIZ

 

Proposed Road Extension

Proposed Road Extension

Designation unique identifier

SWDC55

Designation purpose

Proposed road

Site identifier

Pellikan Place, Tokoroa

Lot 12 DP 377392

Lapse date

Has a lapse period of 10 years (instead of the standard 5-year timeframe)

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: RLZ

 

Proposed Road

Designation unique identifier

SWDC56

Designation purpose

Local Road

Site identifier

Princes St, Putaruru

Lot 100 DP 547758

Lapse date

12 October 2028

Designation hierarchy under section 177 RMA

Primary

Conditions

Yes

Additional information

Underlying Zone: COMZ

Conditions

The designation conditions applying to the use of site SWDC56 are as follows:

1. Except as modified by the conditions that follow and subject to final design, the project works shall be undertaken generally in accordance with the information provided by the Requiring Authority in its Notice of Requirement (‘NoR’), its evidence and supporting documentation, including:

(a) Notice of SWDC’s Requirement for Designation dated 6 October 2022;

(b) Princes Street Road Designation (D59), Addendum to Notice of Requirement dated 8 June 2023, prepared for SWDC by Monocle Consulting Ltd;

(c) Integrated Transportation Assessment, Notice of Requirement: Access Road to GC4 dated 4 June 2023, prepared for SWDC by CKL;

(d) Drawings reference 3000, 3600 and 3601 (Rev 0) dated 9 May 2023 and 3001 (Rev 1) dated 29 May 2023, prepared for SWDC by CKL; and

(e) Desktop Soil Contamination Assessment, Princes Street, Putaruru dated June 2023, prepared for SWDC by 4Sight Consulting.

2. Where there is any inconsistency between the NoR documentation and the designation conditions, the designation conditions shall prevail.

3. The Requiring Authority shall design the road to ensure:

(a) A road width in accordance with the relevant industrial/commercial standard in the WRITS, unless otherwise agreed by the road controlling authority;

(b) Vehicle crossings shall be provided to 129 Princes Street and 139 Princes Street in locations where all traffic movements can be safely completed at the vehicle crossings. This should be demonstrated with vehicle swept paths; and

(c) That the provision for a right turn treatment on Princes Street at the intersection of Princes Street and the Project is not precluded, to ensure this treatment can be provided when necessary in the future.

4. The outline plan for the project works shall:

(a) Describe the consultation undertaken with Waka Kotahi New Zealand Transport Agency at the detailed design phase. A summary of the feedback received from Waka Kotahi shall be provided, along with a description of any changes made to the design as a result of consultation;

(b) Describe the consultation undertaken with both the Raukawa Charitable Trust and the Te Arawa River Iwi Trust at the detailed design phase. A summary of the feedback received from both trusts shall be provided, along with a description of any changes made to the design as a result of consultation;

(c) Contain both written confirmation from the Requiring Authority that a safe systems audit of the detailed design has been undertaken, and a report setting out any changes that were made to the detailed design to reflect the findings of the audit;

(d) Describe the measures that will be employed during the project works to ensure that the owners and occupiers of 129 Princes Street and 139 Princes Street continue to have suitable access to the Council’s potable water, sewerage and stormwater networks, and to electricity and telecommunications infrastructure during all construction works; and

(e) Set out the vegetation removal that is to be undertaken to ensure that the relevant minimum sightlines are available to those vehicles looking to enter Princes Street from the new local road.

5. Not less than twenty (20) working days prior to the commencement of construction, the Requiring Authority shall submit a Construction Management Plan (‘CMP’) to the SWDC’s Planning Manager (‘the Planning Manager’) for certification. The Planning Manager shall only issue their written certificate if they are satisfied that the CMP accords with Condition 6 of this designation.

6. The objective of the CMP is to document the measures that the Requiring Authority will employ to comply with all conditions of this designation during construction and shall include the following:

(a) Details of the Site Manager, including their contact details (name, phone number, postal address, email address);

(b) The proposed start date for the construction works and an outline construction programme;

(c) Construction hours, which shall be managed to ensure compliance with the construction noise standards in condition 9;

(d) The location of any temporary site offices and conveniences (such as portaloos);

(e) The environmental incident and emergency management procedures;

(f) An erosion and sediment control plan which shall be consistent with the WRC’s Erosion and Sediment Control Guidelines for Soil Disturbing Activities: January 2009;

(g) Procedures for controlling dust to achieve compliance with condition 10;

(h) Procedures to be followed in the event that any historic artefacts are disturbed which shall be consistent with the requirements of condition 11;

(i) The measures that shall be employed to maintain access to adjoining properties during normal daytime business hours;

(j) Procedures for ensuring that business and property owners and occupiers in the immediate vicinity of the construction works are given prior notice of the commencement of construction and are informed about the expected duration of the works and any temporary access changes;

(k) The measures that will be employed to ensure the safety of the general public; and

(l) The procedures that will be followed for receiving, responding to and recording complaints.

7. Any proposed changes to the CMP shall be set out in writing by the Requiring Authority and certified (in writing) by the Planning Manager prior to them being implemented. The Planning Manager shall only issue their written certificate if they are satisfied that the proposed changes to CMP accords with Condition 6 of this designation.

8. The Requiring Authority shall undertake the construction works in accordance with the certified CMP and shall ensure that a copy of the certified CMP is kept on-site at all times during the period of construction works.

9. Construction noise shall comply with the provisions of NZS 6803:1999 ‘Construction Noise’.

10. Construction works shall be undertaken in a manner to ensure that the activity does not cause any dust nuisance beyond the designation boundary that is deemed to be objectionable by an Enforcement Officer of the SWDC.

11. The Requiring Authority shall ensure that the following protocol shall be followed in the event that an unidentified archaeological site is located during construction works:

(a) Work shall cease immediately at that place and within 20m around the site;

(b) The contractor shall immediately shut down all machinery, secure the area, and advise the Site Manager;

(c) The Site Manager shall secure the site and notify the Heritage NZ Regional Archaeologist. Further assessment by an archaeologist may be required;

(d) If the site is likely, in the opinion of the Site Manager, to be of Māori origin, the Site Manager shall notify the Heritage NZ Regional Archaeologist and the appropriate iwi groups or kaitiaki representative of the discovery, and ensure site access to enable appropriate cultural procedures and tikanga to be undertaken, as long as all statutory requirements under legislation are met (Heritage NZ Pouhere Taonga Act 2014, Protected Objects Act 1975);

(e) If human remains (koiwi tangata) are uncovered the Site Manager shall advise the Heritage NZ Regional Archaeologist, NZ Police and the appropriate iwi groups or kaitiaki representative, and the process under (d) above shall apply. Remains are not to be moved until such time as iwi and Heritage NZ have responded;

(f) Works affecting the archaeological site and any human remains (koiwi tangata) shall not resume until Heritage NZ gives written approval for work to continue. Further assessment by an archaeologist may be required;

(g) Where iwi so request, any information recorded as a result of the find, such as a description of location and content, is to be provided for their records; and

(h) Heritage NZ will determine if an archaeological authority under the Heritage NZ Pouhere Taonga Act 2014 is required for works to continue.

Advice Notes: 

1. This designation will lapse 5 years after it is included in the district plan unless it is given effect to before the end of that period or the time period is extended pursuant to section 184A(2)(b) of the RMA.

2. The Requiring Authority is responsible for obtaining any resource consents that may be required for the works that are the subject of this designation.

3. A Detailed Site Investigation will be required to determine whether resource consents will be required under the National Environmental Standard for the Assessment and Management of Contaminants in Soil to Protect Human Health

Requiring Authority: TPR – Transpower New Zealand Ltd

The purpose of a substation is to receive electricity from a generator or high voltage transmission lines and transform and transport energy to a point where the local power company (Powerco Ltd), via the local power company’s own distribution lines, can distribute the electricity to customers. A telecommunications system is required to co-ordinate and control the operations of substations, which is controlled remotely.

 

Arapuni Outdoor Switchyard

Designation unique identifier

TPR01

Designation purpose

Outdoor switchyard

Site identifier

Arapuni

Section 1 Block XII, Maungatautari SD

SO 59581

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: SPZ-ELG

 

Hinuera Substation

Designation unique identifier

TPR02

Designation purpose

Electricity substation

Site identifier

Corner Lake Road/State Highway 27

Pt Lot 6 4987

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ

 

Kinleith Substation

Designation unique identifier

TPR03

Designation purpose

Electricity substation

Site identifier

Old Taupo Road,

Lot 1 DPS 62238

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GIZ

 

Waipapa Outdoor Switchyard

Designation unique identifier

TPR04

Designation purpose

Outdoor switchyard

Site identifier

Waipapa

Lot 1 DPS 89582

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: SPZ-ELG

 

Brownhill Road – Whakamaru North A 400KV Transmission Line

Designation unique identifier

TPR05

Designation purpose

Electricity transmission and ancillary purposes

Site identifier

Whakamaru north to Waipa District boundary north of Arapuni

Lapse date

Has been given effect

Designation hierarchy under section 177 RMA

Primary

Conditions

No

Additional information

Underlying Zone: GRUZ